Testing with simulations in preparation for the cesm3_0 release for the scientifically supported resolution #513
The plan for the scientifically supported simulation for MizuRoute with CTSM is:
2000 year conditions fixed (final year might be 2020 or something else)
1-degree
HDMA-lake
either g17 mask (POP mask) or t232 MOM mask (hopefully the later if it works)
clm6_0
SP Satellite Phenology mode
CRUJRA2024 forcing
Run for 20 or 30 years, doing the normal cycling over years centered about the fixed year
Activity
ekluzek commentedon Mar 9, 2026
CRUJRA2024 forcing (and the update CRUJRA2024b) is now available. The compsets in CTSM should be updated to point to it.
We had trouble with f09_f09_mt232, so likely won't do that for mizuRoute.